Skip to main content

Commissioning and Testing Data Center Automation Systems

By NFM Consulting 1 min read

Key Takeaway

Commissioning and testing process for data center automation — FAT, SAT, point-to-point checks, functional testing, failover validation, and IST procedures.

Quick Answer

Commissioning verifies that all data center automation systems — SCADA, BMS, PLCs, power, and cooling — operate correctly individually and as an integrated system. The process progresses from factory acceptance testing (FAT) through site acceptance testing (SAT), point-to-point verification, functional testing, and integrated systems testing (IST).

Commissioning Phases

  • FAT — Verify PLC, SCADA, and control panel operation at the vendor's facility before shipping
  • SAT — Verify equipment operates correctly after installation at the data center
  • Point-to-Point (P2P) — Verify every sensor, actuator, and control output matches its SCADA/BMS tag
  • Functional Testing — Simulate faults and verify automated responses (generator start, ATS transfer, cooling switchover)
  • IST — Full scenario testing with all systems operating together under real and simulated conditions

Failover Testing

Test every redundancy and failover sequence: utility loss → generator start → ATS transfer → UPS bypass → cooling lead/lag switch. Document results for compliance.

Load Bank Testing

Use resistive load banks to simulate full IT load on generators and UPS systems. Verify runtime, transfer switching, and load shedding logic under controlled conditions.

IST Requirements

Uptime Institute Tier III and IV certification requires IST demonstrating concurrent maintainability and fault tolerance. TIA-942 also defines commissioning requirements. All test results must be documented with sign-off.

Handover

Deliver as-built drawings, test records, alarm setpoint documentation, and O&M manuals to the facility operations team.

Frequently Asked Questions

Ready to Get Started?

Our engineers are ready to help with your automation project.